ANGA - PROGRESS OF INVESTMENT July 2025 plot fencing taken place July 2025 plot fencing taken place August 2025 mock up room and ground works starting August 2025 mock up room and ground works starting September 2025 landscaping works commenced September 2025 landscaping works commenced October 2025 mock up room structure completed October 2025 mock up room structure completed November 2025 Main building groundworks works commenced November 2025 Main building groundworks works commenced December 2025 main building foundation works IN PROGRESS and mock up room works in progress December 2025 main building foundation works IN PROGRESS and mock up room works in progress January 2026 Mock up room finishing works in progress January 2026 Mock up room finishing works in progress February 2026 Mock up room landscaping in progress February 2026 Mock up room landscaping in progress February 2026 Main building foundations works in progress February 2026 Main building foundations works in progress March 2026 Main buildings foundations completed March 2026 Main buildings foundations completed March 2026 Ground floor structural works commenced and in progress March 2026 Ground floor structural works commenced and in progress April 2026 Ground floor structural works completed April 2026 Ground floor structural works completed April 2026 1st floor structural works commenced April 2026 1st floor structural works commenced May 2026 Anga 4 bedroom mock up room finishing works in progress May 2026 Anga 4 bedroom mock up room finishing works in progress June 2026 Anga 4 bedroom mock up room finishing works completed June 2026 Anga 4 bedroom mock up room finishing works completed June 2026 Anga mock up room opening ceremony June 2026 Anga mock up room opening ceremony June 2026 Top floor mechanical, electrical, and plumbing works commenced June 2026 Top floor mechanical, electrical, and plumbing works commenced July 2026 1st floor structural works in progress July 2026 1st floor structural works in progress August 2026 1st floor structural works completed August 2026 1st floor structural works completed September 2026 2nd floor structural works commenced and in progress September 2026 2nd floor structural works commenced and in progress October 2026 2nd floor structural works completed October 2026 2nd floor structural works completed October 2026 3rd floor structural works commenced and in progress October 2026 3rd floor structural works commenced and in progress November 2026 3rd floor structural works completed November 2026 3rd floor structural works completed November 2026 4th floor structural works commenced and in progress November 2026 4th floor structural works commenced and in progress December 2026 4th floor structural works completed December 2026 4th floor structural works completed December 2026 5th floor structural works commenced and in progress December 2026 5th floor structural works commenced and in progress January 2027 5th floor structural works completed January 2027 5th floor structural works completed January 2027 6th floor structural works commenced and in progress January 2027 6th floor structural works commenced and in progress February 2027 6th floor structural works completed February 2027 6th floor structural works completed March 2027 Top floor structural works commenced March 2027 Top floor structural works commenced CURRENT PROGRESS – LIVE CAM Track your investment in a real time camera view ANGA - GALLERY 2026 – JUNE Building the Foundation of ANGA Premium Space 2026 – MAY Advanced structural works are in progress. 2026 – APRIL Block B Moves Forward Block C Reaches the Next Level 2026 – MARCH Foundations Complete, Columns Rising Exterior Works Completed 2026 – FEBRUARY Reinforcement Grids Ready for the Next Stage Landscaping & External Areas in Progres Structural Works Underway & Final Details in Progress 2026 – JANUARY Site Preparation – Perimeter Secured & Branded Site Infrastructure – Utilities & Drainage Installation 2025 – DECEMBER Foundations Continue & Mock-Up Takes Shape 2025 – NOVEMBER Main Building Groundworks Begin 2025 – OCTOBER Main building groundworks underway – septic and water tanks, foundation prep The ANGA mock-up room structure is complete. 2025 – SEPTEMBER Great progress at the Anga Zanzibar site! We’re thrilled to announce that the mock-up room is officially up. 2025 – AUGUST Walls for the Mock-Up Room are Up! Foundation Works Finalised & Mock-up Unit Structural Works Underway Early Landscaping & Mock-up Unit Foundations Finalised 2025 – JULY Groundworks Initiated & Mock-Up Unit Construction Commenced Site Securing & Boundary Fencing Completed